Gamma Races To Complete Foundation For East Side Tower To Beat Rezoning

3 Sutton Place As Of October 2016

Gamma Real Estate's Sutton Place tower is in danger of seeing major delays, thanks to a controversial rezoning process in city council.

On Nov. 16, the City Planning Commission voted to approve a rezoning of 10 blocks of the Upper East Side neighborhood that would prevent future skyscrapers like Gamma's Sutton 58 project, but with a grandfather clause allowing the 800-foot condo tower to continue. Councilman Ben Kallos, who represents the area, is attempting to remove that clause before it hits the greater city council for a vote, The Real Deal reports.

If the Council approves the change, Gamma would have to apply to the Board of Standards of Appeals to complete the project. BSA guidelines stipulate that if the foundation has made "significant progress," then work can continue despite a rezoning. Gamma founder and CEO Richard Kalikow claims that the foundation for the tower at 3 Sutton Place is three weeks away from completion, but even if the appeal to the BSA is successful, the process would take months.

“The only upshot of removing the grandfathering clause would be to punish us monetarily, but also to displace and furlough a bunch of workers who really don’t deserve it,” Kalikow told a zoning subcommittee hearing, according to TRD.

Lendlease Construction is the general contractor on the project, and an employee testified that such a delay would "stop [his] life" and the lives of his family. Kallos said that removing the grandfather clause could delay a council vote on the rezoning until after the foundation is fully complete, which would also allow the construction to continue uninterrupted.

Gamma and Lendlease are doing all they can to remove the uncertainty and complete the foundation, applying for and receiving multiple after-hours construction exemptions from the Department of Buildings since June 3 to work on Saturdays, according to TRD. Gamma purchased the development site from Bauhouse Group in a foreclosure auction in December 2016 after its loan to Bauhouse went into default.

Continue reading this story with a free account

Log in or register
Sign up for more articles like this
Subscribe to Bisnow's New York Newsletters
Related Stories

Supertall Assemblage Comes Together At Long-Vacant Midtown Site: The N.Y. Deal Sheet

Fannie Mae, Freddie Mac Rewrite Underwriting Standards For NYC's Rent Freeze

Former Randolph Event Venue Planned For 200-Room Hotel, Theater

Banks Are Manhattan's Latest Hot Retail Tenant

Taiwan Semiconductor Manufacturing Co. Could Expand In North Texas

RXR Marketing Executive Lauren Maturo Dies At 32

Weil Gotshal Wind-Down Leaves 830K SF Hole In America's Office Market

EXCLUSIVE: Downtown Houston+ Targets Grocery Gap, Pedestrian Experience With New Programs

140-Acre Attleboro Golf Course Hits Market, Pitched For Redevelopment

Meet Bisnow's 2026 New York Power Women Honorees

Related, Oxford Land Tenant For Top Floors Of 70 Hudson Yards

BXP Execs See Better Returns In Building Offices Than Buying Them