Seattle Center Arena's 'Floating' Roof Attached

Courtesy of Mortenson Construction
Mortenson Construction Recently Completed Work On The Suspended Roof At The Seattle Center Arena.

Mortenson Construction recently raised the 44 million-pound roof of the Seattle Center, marking a new phase in the massive $1B project.

The latest lift was completed with 72 temporary steel columns, cross beams and a steel reinforcement structure called a kickstand.

Once finished, the roof is designed to appear as though it is floating. Prior to the redesign, the arena’s roof was supported by 20 concrete Y-columns and four giant buttresses.

The $1B project is privately financed and is a collaboration between Oak View Group, CAA Icon, Thornton Tomasetti, Hart Crowser, Mortenson and Populous. It is set to deliver in summer 2021 in time to host the NHL’s Seattle team’s first season.

Though heavy, the suspended roof is considered safe and is covered with sensors. It is designed to withstand both wind and earthquakes, and engineers are following guidelines by the American Society of Civil Engineers’ codes and standards for “design loads during construction.”

Contractors are currently 75% of the way through excavating 600,000 cubic yards of dirt to increase the arena bowl’s size. Once complete, the building will have a 17,400-person capacity for hockey and an 18,600-person capacity for WNBA games. It is expected to host 140 events per year.

Continue reading this story with a free account

Log in or register
Sign up for more articles like this
Subscribe to Bisnow's Seattle Newsletters
Related Stories

Historic Brooklyn Hotel To Be Turned Into Ritz-Carlton-Branded Condos

Philly Has The Fundamentals. Now It Has To Reduce The Risk Of Building

Design Plans Revealed For RFK Stadium Parking Garages, Headed To Review

SpaceX Sues Texas AG, Grimes County Over Terafab Project Information

Retail Dynasty Pushes Button On Pair Of London Coliving Schemes

1,300 Projects Potentially Paused Due To Suspension Of Quality Inspectors

EXCLUSIVE: Georgia-Pacific Scraps Conversion Plans For Its Atlanta HQ

Miami Is 'Desperate' For A New Office Tower. It's About To Get 2

Sea Wall Rehabilitation: Strengthening Hudson River Walkway For Next 100 Years

Feds Raid North Texas-Based Contractor As Part Of HUD Investigation

Brooklyn's The Hall Complex To Get Hundreds Of Units, Synagogue And Office In New Plans

A Mindful Approach To Building In Specialized Environments