California Forever Scraps Ballot Initiative For New City After Critical County Report

A group of tech billionaires behind the so-called California Forever project to develop a new city in Solano County, California, is changing strategies after a report questioned the project’s financial feasibility.

California Forever will no longer pursue a ballot initiative to amend the county plan and rezone 17,000 acres for development and will instead seek approval through typical county processes, The Mercury News reported.

Solano County issued a report July 18 that said infrastructure for the project, including schools, parks and related expenses, would cost an estimated $6.4B for the development’s first phase. To complete the new city, the bill came to an estimated $50B, according to The Mercury News.

Costs for other services, like fire protection, would outpace revenues, and the loss of farmland would cut agricultural production by $6.7M annually, the report said. The availability of water, an increasingly crucial component of any development in the West, was an open question, according to the report.

California Forever, backed by big Silicon Valley names like Marc Andreessen and Laurene Powell Jobs, spent more than $800M on 60,000 acres of mostly agricultural land in Solano County for the establishment of the new city. The proposal was met with skepticism by many locals, while others expressed excitement about the boost to the local tax base and thousands of new jobs and housing units.

The land’s proximity to Travis Air Force Base also raised eyebrows at a federal level because roughly 3% of the dollars to purchase the land came from foreign investors. And some in Solano County resisted selling their land, touching off a legal dispute in which California Forever’s real estate operation, Flannery Associates, sued landowners for $510M.

In a statement posted to the project’s website, California Forever CEO and co-founder Jan Sramek said his organization was trying to move faster than usual for large-scale developments by getting zoning approvals before conducting an environmental impact report. But in light of the county’s report, the group will now reverse its plans.

California Forever will work on an environmental impact report and development agreement over the next two years, then bring the entire proposal for approval in 2026, according to Sramek’s statement.

Continue reading this story with a free account

Log in or register
Sign up for more articles like this
Subscribe to Bisnow's San Francisco Newsletters
Related Stories

Former Randolph Event Venue Planned For 200-Room Hotel, Theater

Orchard Partners Selects JLL To Market 892K SF Manufacturing Campus In Brisbane: The San Francisco Deal Sheet

Taiwan Semiconductor Manufacturing Co. Could Expand In North Texas

EXCLUSIVE: Downtown Houston+ Targets Grocery Gap, Pedestrian Experience With New Programs

140-Acre Attleboro Golf Course Hits Market, Pitched For Redevelopment

Foundry Robotics Leaves San Francisco For New East Bay HQ

Capital Flooded Into Bay Area Apartments. Then Treasury Yields Spiked

Data Centers Lose The Top Spot, San Francisco Jumps 40 Places: 9 Takeaways From ULI's 2027 Outlook

As The Future Of The Office Continues To Evolve, WeWork Is Bringing Clients A Tailored Workplace Solution

Autonomous Construction Vehicle Startup Bedrock Hits $4.1B Valuation

Developers Up Sunny Isles Beach St. Regis Debt Again With $463M Loan

One Week. 2 Schemes. More Than 2,000 London Homes Cancelled