Kushner Cos. Blames One Journal Square's Delays, Possible Failure On Politics

Much like at 666 Fifth Ave., Kushner Cos. could be seeing its ambitious development plan at One Journal Square in Jersey City go up in smoke.

Kushner Cos KABR Group
Rendering For The Planned One Journal Square Development In Jersey City By Kushner Cos. And Kabr Group

The dual-skyscraper proposal that Kushner wants to develop along with KABR Group has been on the rocks since WeWork pulled out as an anchor tenant and investor in May, and the Jersey City Redevelopment Agency put it on even thinner ice by declaring the developers had violated the terms of their agreement with the city, Hudson County View reports.

The JCRA cited a combination of factors in pulling support for One Journal Square. Primarily, the lack of WeWork caused a change in plans that made the proposal a "more traditional residential project," JCRA acting Executive Diana Jeffrey said. The JCRA also said that Kushner was nearly a year late in paying administrative fees and had proposed an abundance of plan changes.

Jersey City Mayor Steven Fulop tweeted his support for the JCRA's decision, stating his hopes that One Journal Square can "move to a different partner that can complete the project."

WeWork's departure also took away a sizable chunk of funding for the project, which Kushner and KABR have not been able to replace to date. Charles Kushner met with Fulop in January to discuss additional subsidies, but the mayor has been strident in his opposition.

Many have asked about the Kushner’s project in #JerseyCity - this reporter has been following the back/forth between the lawyers. There is a sense of entitlement that the developer has towards a subsidy - we as a city just don’t see it the same way https://t.co/2klVcB0dV1

— Steven Fulop (@StevenFulop) April 17, 2018

After the apparently fruitless meeting between Fulop and the Kushner patriarch, lawyers for the development group sent a letter to the city claiming that its officials "suddenly and unexpectedly" cut off discussions regarding the project though a draft of building plans had been "nearly completed," Northjersey.com reports.

Kushner Cos. has since released a statement accusing Fulop of "playing politics" by pulling his support for the project for no reason other than former CEO Jared Kushner's connections to President Donald Trump. Fulop tweeted his response Monday evening.

My job is #jerseycity progress + while I disagree w/everything about the President, this decision stands on its own merit. After 6 yrs of delay after delay from them, I think fair to say that the Kushners shouldn’t point fingers https://t.co/B8X7419RtO

— Steven Fulop (@StevenFulop) April 24, 2018

Continue reading this story with a free account

Log in or register
Sign up for more articles like this
Subscribe to Bisnow's New Jersey Newsletters
Related Stories

Supertall Assemblage Comes Together At Long-Vacant Midtown Site: The N.Y. Deal Sheet

Fannie Mae, Freddie Mac Rewrite Underwriting Standards For NYC's Rent Freeze

Starwood Launches Residential Land JV Targeting $1B In Annual Originations

RealPage Antitrust Case Ends With Nearly $360M In Settlements For Renters

ZOM Living Entity Files For Bankruptcy To Fund Fight To Overturn $323M Judgment

How Colliers Engineering Helped A Struggling Dam Move To The Head Of The Class

Former Randolph Event Venue Planned For 200-Room Hotel, Theater

Real Estate's Bottom Rung Is Getting Harder To Reach — And Now It Wants AI Skills

Banks Are Manhattan's Latest Hot Retail Tenant

OpenAI Plans Data Center Rebrand To Make Projects Palatable To Voters

The Geo Group To Reopen 2,329-Bed Immigration Facility In Texas

Brookfield, CPP Complete $5.2B REIT Buyout, Pick Up U.S. Logistics Assets