A Closer Look At RagingWire's TX1 Data Center

RagingWire's new data center campus sits on 42 acres on the edge of Garland and Richardson. The 1M SF campus will deliver with 80MW. RagingWire VP Jim Leach built a team to make the project Texas ready.

JLL managing director Bo Bond helped RagingWire lock down a site in Garland. The reasoning: It's where users want to be, and there's the ability for scale and good transportation infrastructure.

The site's location on the border of Garland and Richardson allows for two sets of substations, one through Garland Power and Light and the other through Oncor.

RagingWire's in-house design and construction teams worked with Page to design the project around worst-case scenarios, Page principal John Major says. An EF3 tornado with winds up to 165 mph can't shake TX1.

The North Texas heat posed a challenge for the center, but Air Enterprises VP John Kolar and his team formatted the heat wheel exchanger to reject heat. The efficiency of the heat exchanger has a lot of partial, or shoulder, hours.

Here are John Major, Jim, Bo and John Kolar.

The team also planned for the future by removing water. You can't get an SLA on water, Kolar says, so there's been a big push in the industry to get rid of water in cooling systems.

The project will have cooling and control systems that react to variances so 40KW cabinets can sit next to 2KW cabinets, John Major says.

The next phases of the project will undoubtedly adapt to keep up with innovation. As John Major puts it, you can't predict the future, you can only get ready for it.

Continue reading this story with a free account

Log in or register
Related Topics: Bo Bond , Jim leach , John Kolar , John major , PAGE , RagingWire , Tx1
Sign up for more articles like this
Subscribe to Bisnow's Dallas-Fort Worth Newsletters
Related Stories

Carrier To Invest $600M In Fort Worth Advanced Manufacturing Facility

Trump: Data Centers 'Mandated' To Supply Own Electricity, Should Pay 'Dividend' To Communities

Venu Closes $60M Sale-Leaseback Deal For McKinney Concert Venue Land

Making Data Center Construction Supply Chains Smarter

Trammell Crow Breaks Ground On Office-To-Resi Conversion In Dallas: The DFW Deal Sheet

CoreWeave's Debt Troubles Fuel Fears Of An AI Data Center Reckoning

CBRE Expands Data Center Footprint With $1B Acquisition Of Onnec Group

Senate Bill Offers Data Centers A Faster Path To Power, But At A Price

Illinois Voters Weigh Data Center Referendums On November Ballot

DFW Industrial Thrives As Tenants Seek Quality, Flexibility And Power

Plano Voters To Decide On New Taxes Tied To Dallas Stars' $3B Sports And Entertainment District

Regulators Reject Proposed Rules For Data Centers On Nation's Largest Grid