After a court vacated DC's approval of the $720M McMillan Sand Filtration Site development in December, the team behind the 25-acre project has just responded with a detailed justification for its plans.

Vision McMillan Partners, a JV of Jair Lynch, Trammell Crow and EYA working with the Office of the Deputy Mayor for Planning and Economic Development, submitted documentation to the Zoning Commission arguing that decreasing its density would undermine Comprehensive Plan objectives and jeopardize the project's success, UrbanTurf reports.

For the 25-acre site, the team proposed building 1M SF of healthcare space, 655 housing units, 125K SF of retail anchored by a Harris Teeter, a 17K SF community center and an eight-acre park. The project had received Zoning Commission approval, but then community group Friends of McMillan Park successfully sued to have that approval vacated. The court gave the development team the opportunity to prove its project would not harm the surrounding community and better justify its density.

The District Court of Appeals wrote in its decision the reason for needing high-density development, rather than moderate density, was not adequately explained. Vision McMillan's response focused on the project's healthcare facility. It said reducing the project to moderate density would mean cutting two floors from this building, which would reduce its chances of landing an anchor tenant and hurt the viability of the project's retail.

As for the impacts on the surrounding community, the team argued that adding housing to the area would help mitigate the effects of gentrification and the project would not displace any residents. It also said the healthcare component would provide newer facilities for underserved neighborhoods.

The Zoning Commission will hold a new hearing for the development on March 23.

Continue reading this story with a free account

Log in or register
Sign up for more articles like this
Subscribe to Bisnow's Washington, D.C. Newsletters
Related Stories

270-Unit Manassas Gated Community Sells: The D.C. Deal Sheet

King Of Prussia Pursues Stadium To Anchor $200M Mixed-Use Complex

BXP Closes In On Next D.C. Office Development As It Shrinks Assets

How Metropolis Is Bringing Parking Into The Future With AI And Recognition Technology

Montgomery County Approves 18-Month Data Center Moratorium

With New $250M Deal, Elme Is Fully Set To Liquidate

Simpson Thacher Appears In Talks For What Could Be One Of D.C.'s Largest Office Leases In 2026

Hines Nabs 4 Prince William Housing Sites: The D.C. Deal Sheet

1200 White St., Atlanta's Newest Creative Hub, Is Transforming The West End

AvalonBay Sells 217-Unit Community Next To Greensboro Metro

GSA Head Says Federal Government Has 'Place To Play' In Southwest D.C. Redevelopment

Downtown D.C. Office In Receivership Hits Market For Conversion