Labor Shortages And High Construction Costs Hinder Delivery Of 3,534 Units In Dallas

Labor shortages and high construction costs have pushed back the completion of 3,534 Dallas apartments into 2018, according to the Dallas Business Journal.

Axiometrics research shows Dallas is the market most affected in a national slowdown of construction deliveries. Major cities in the midst of multifamily booms, like Dallas, are feeling the greatest slowdown.

According to Axiometrics estimates, 15% of apartment completions were pushed from 2016 into this year. The firm estimates the same for this year going into next year. The total estimated number of units delayed nationwide is 56,186 units. New York and Houston trail Dallas, with 3,371 and 3,036 units delayed, respectively.

Continue reading this story with a free account

Log in or register
Sign up for more articles like this
Subscribe to Bisnow's Dallas-Fort Worth Newsletters
Related Stories

McKinney Approves $21M In Funding For Cannon Beach Surf Resort

Google Delays Thompson Center Opening To 2028, Releases New Renderings

Sovereign Fund Backs £500M Subterranean West End Development

Historic Brooklyn Hotel To Be Turned Into Ritz-Carlton-Branded Condos

Machine Investment Group Buys 490-Unit Multifamily Property In North Dallas: The DFW Deal Sheet

Philly Has The Fundamentals. Now It Has To Reduce The Risk Of Building

Design Plans Revealed For RFK Stadium Parking Garages, Headed To Review

DFW Multifamily Distress Creates Opening For Investors As Development Slows

SpaceX Sues Texas AG, Grimes County Over Terafab Project Information

DFW's Life Sciences Sector Offers Startups The Ingredients They Need To Scale

Dallas Mavericks Launch Plans For New Arena-Anchored Entertainment District

Shorenstein Acquires Preston Center Office Tower: The DFW Deal Sheet