Apartment Projects Stall, Pushing Timelines Out 500 Days

Photo of a new home under construction

Apartment developers are having a hard time getting their high-rises to rise.

It is taking an average of 500 days for new projects to break ground after they are approved, a 45% jump from 2019, the Wall Street Journal reported based on Yardi Matrix data.

The usual suspects, high interest rates and a strict lending environment, are the primary drivers, and many developers are deciding to stall projects until profit margins improve.

Regional banks are tightening their lending on commercial real estate as their residential portfolios aren't offering favorable returns. Projects look less profitable, as property values dropped up to 30% from a 2022 April high.

Stagnant rent growth doesn't benefit developers' financing efforts either. Rents fell 0.8% year-over-year and have been negative since last year, according to Apartment List.

An apartment surplus in some markets is contributing to rents decreasing, making investors wary of adding more buildings to their portfolios.

Construction spending is at a high. $890B was put into residential builds in April, according to Census data, far above the $865B spent by the end of last year.

But overall, April wasn't the greatest month for multifamily.

The asset class led the national distress rate, which overall hit a new high of 8.35%. Multifamily's rate jumped from 3.7% in March to 7.2%.

More than $1.6B worth of multifamily CMBS loans went to special servicing in April, Trepp found. Looking ahead, $150B worth of loans are set to mature by the end of 2025, and $525B worth on 58,000 properties are due within five years.

With the struggle to secure financing, the picture could get worse for distress rates as the year goes on.

Continue reading this story with a free account

Log in or register
Sign up for more articles like this
Subscribe to Bisnow's National Newsletters
Related Stories

Bisnow's 2026 DEI Data Series

America's Data Centers Are Running Out Of People Who Know How To Run Them

Ruben Cos. Says It Can't Sell, Finance Navy Yard Multifamily Project

Why Data Centers Crave Simplicity As Operations Grow More Complex

Blackstone Looks To Secondary Market To Cash Out Investors In $11B Fund

Ares, Canadian Pension Investor Launch $2.4B U.S. Logistics JV

Troubled Multifamily Loans Face A Refinancing Problem: Who Puts In New Equity?

Toys R Us Plans 120 New Stores Ahead Of The Holidays

NYC Pushes To Use Opportunity Zone 2.0 For Mamdani's Housing Goals

DOJ Charges LA Nonprofit Workers With Misusing $8.7M Meant For Housing Aid

Data Center Leaders Aren't Sweating Calls For An AI Slowdown

REPORT: Amazon Eyes Next Industrial Push With Plans To Expand Same-Day Deliveries