Blackstone's QTS Abandons Digital Gateway Project, Ends Legal Fight

Blackstone’s QTS is stepping away from a massive data center plan in Prince William County and has dropped its legal effort to pursue the project.

“After careful consideration, QTS has made the decision to terminate the Digital Gateway project and withdraw its associated filings,” QTS said Friday in an emailed statement to Bisnow.

data center data centers server rack

Blackstone’s data center arm on Thursday notified the Virginia Supreme Court that it was withdrawing its petitions to appeal a lower court decision that voided the rezoning approvals needed for the PW Digital Gateway project to move forward.

QTS executives decided the litigation wasn't worth pressing forward, according to Bloomberg, which first reported the news.

The decision is a win for landowners, advocacy groups and other opponents who had been fighting against the project. If it had proceeded, the Digital Gateway project could have become one of the largest data center clusters in the world.

QTS’ withdrawal was a result of the plaintiffs’ legal strategy and public pressure on the county board, said Craig Blakeley, a member of Alliance Law Group and counsel for Oak Valley Homeowners Association, the lead plaintiff in the litigation.

“The legal arguments we presented allowed the courts to see through our opponents’ attempts to confuse the issues and correctly decide the case based on the facts and the law,” Blakeley said in an email.

In April, the Board of County Supervisors dropped its legal defense of the 2,100-acre rezoning effort following the Virginia Court of Appeals ruling. Compass Datacenters, the other developer in the project, abandoned the fight. But QTS appealed to the state’s top court.

QTS said in its statement on Friday that the project would have delivered “tens of billions of dollars in capital investment, substantial annual local tax revenues to support public services, and thousands of long-term jobs.”

It said it will move forward with “a responsible and orderly termination of project activities.”

UPDATE, JULY 3, 6:15 P.M. ET: This story was updated with a comment from counsel for the Oak Valley Homeowners Association.

Continue reading this story with a free account

Log in or register
Sign up for more articles like this
Subscribe to Bisnow's Washington, D.C. Newsletters
Related Stories

Regulators Reject Proposed Rules For Data Centers On Nation's Largest Grid

How Thermal Imaging Provides Proactive Security Measures For Data Centers

Fairfax Pays $23M For Innovation Center Site, With Plans For Affordable Housing

Blackstone-Backed Data Center Firm AirTrunk Reportedly Delaying $1.5B IPO

From Precast To Conservation: Addressing Today's Stormwater Challenges

Political Campaigns Have Spent $87M Making Data Centers A TV Villain

Developer Inks Deal To Move HQ To Lerner's Tysons Tower

Soar AI Secures $1B Equity For Industrial-To-Data-Center Development

Industrious Takes Top Floors In Downtown Lease: The D.C. Deal Sheet

Transformers: Yet Another Data Center Power Infrastructure Supply Chain Bottleneck

Distress Divide: How Private vs. Institutional Investors Are Thinking About D.C. Office

Scottish Castle In Middle of Growing Controversy Over Data Centre Development